Soccer fields, sports courts, a dog park and a playground are planned for the Lone Tree development in Van Alstyne, according to a state filing that puts the work at $3.75 million, while a separate filing this week lays out a new office building on Texana Street.
Both turned up in the architectural barriers database of the state's licensing agency, TDLR, where builders register projects for accessibility review. We could not find a public announcement of either one.
Lone Tree park
The park filing, titled Lone Tree Park Improvements, was registered Sept. 23. It places the project on Lot 31X, Block A, of Lone Tree and lists:
- sports courts
- soccer fields
- a dog park
- a playground
- a 792-square-foot restroom building
Work is scheduled from Oct. 1, 2026, to May 31, 2027, at an estimated cost of $3.75 million. The owner is JBZ Lone Tree LLC of Grapevine, and the design firm is JVC Group of Plano.
The filing describes the park as privately funded, on private land and for private use. The state database lists its review as complete.