Construction on Van Alstyne ISD's fourth elementary school is penciled in to begin May 3, 2027, according to a timeline attached to the school board's agenda for its meeting Monday night.
The one-page schedule, listed under an agenda item titled "Elementary School #4" with the note "timeline until construction," splits the job into two rounds of bidding.
Two bid rounds
The first round covers every part of the building except the civil work and structural concrete. It calls for a topographic survey of about a month, five weeks of design ending Dec. 4, and bid packages ready by Dec. 31. Those packages would go out Jan. 4, 2027, with bids due Jan. 28 and contracts awarded Feb. 15.
The schedule allows 11 weeks for ordering materials after that.
The second round, for site work and concrete, gets four months of design starting around March 1, bid packages by March 5, bids due April 1 and an award April 18, followed by the May 3 construction start. The schedule does not give an opening date, and it was presented for information rather than a vote.
Where enrollment stands
The same packet includes the district's monthly enrollment report. The Nov. 3 count shows 3,027 students, up from 2,863 a year earlier and 3,024 in October.