Developer would buy 6 acres in Cold Springs Industrial Park for spec buildings, with an option on 10 more

The economic development board votes Thursday, Nov. 5, on selling the tract to Bradford Development at $2.65 a square foot. A separate buyer planning up to 175 jobs is asking for more time.

Dana Whitlock· AI-assisted, edited by Jake Team

October 31, 20262 min read

Industrial Park Development - illustration, Jake Team LLC

A Dallas-based developer would buy about 6 acres in Van Alstyne's Cold Springs Industrial Park for speculative industrial buildings, with an option on 10 more acres, under a contract the city's two development corporations take up Thursday, Nov. 5.

The Economic Development Corporation board will consider a joint resolution with the Community Development Corporation, which co-owns the land, approving a sale to Bradford Development Company. The board meets in a special called session at 6 p.m. at City Hall, 152 N. Main Drive.

The terms

The contract in the board packet covers a 6.257-acre tract, Lot 9R of the park's Phase 2 addition, at $2.65 a square foot, or $722,270.54. The final price would be adjusted to the acreage in a closing survey.

Staff describe that figure as a reduced price negotiated to get building started quickly. Bradford would put down $50,000 in earnest money and have 120 days to inspect the property. After closing, it would have 12 months to buy the neighboring Lot 10R, about 10 acres, on the same terms. The contract also needs City Council approval.

Bradford plans speculative, or "spec," industrial buildings meant to draw new businesses, according to staff. In their report, staff argue that most companies hunting for industrial space start with buildings that already exist, citing figures that 80% to 90% of such searches begin that way, and that there is little of that kind of space along the northern U.S. 75 corridor.

Having a developer build it moves the cost and risk off the city, the report says.

A second buyer needs more time

The board will also vote on extending a separate deal. Advanced Process Solutions, which is buying about 9 acres from the corporation in the same park, has asked for more time while it waits on reports from outside consultants, according to staff. The company plans a 100,000-square-foot building and up to 175 jobs over five years.

The amendment in the packet would end the company's inspection period on the later of a November date or approval of its application to the Texas Semiconductor Innovation Fund, and no later than July 1, 2027. Staff wrote that the company asked for an extension to Nov. 25.

New faces on the board

Four new members join the economic development board at this meeting: Kerri Cook, Tyler Hall, Amanda Hofer and Ryan Shafer. Because the board's president and vice president are no longer serving, the first order of business is electing a president to run the meeting, followed by the other officers.

The agenda also lists a closed-door discussion of a project code-named Project Smiley, with possible action afterward.

Sources

cityofvanalstyne.civicweb.net

cityofvanalstyne.civicweb.net

Share

Dana Whitlock· AI-assisted, edited by Jake Team

Dana Whitlock reports on small business, new openings, and Main Street growth in Van Alstyne.